According to a report by Economic Daily News, Supermicro’s ongoing financial crisis has reportedly led to the suspension of its planned expansion at its Malaysia facility, which was set to double its production capacity. This disruption has prompted Supermicro’s major client, Malaysia’s largest conglomerate and a top NVIDIA AI server buyer, YTL Group, to shift its substantial AI data center order.
The same report indicates that YTL Group is now turning to Wistron Group’s Malaysian subsidiary, Wiwynn, for nearby support to fulfill the order, which involves substantial deliveries of NVIDIA’s high-end GB200 NVL72 full-rack servers.
Industry insiders cited by Economic Daily News previously speculated that NVIDIA would lead any order reallocation; however, this shift originates from Supermicro’s client, YTL Group, whose choice of Wiwynn is strategic. Wiwynn’s plant is situated near Supermicro’s new facility in Malaysia, offering a geographical advantage and boasting robust AI server capabilities.
YTL Group has strong ties with NVIDIA. In March, YTL Power, a subsidiary of YTL Group, announced a partnership with NVIDIA to install DGX GB200 NVL72 AI server systems, aiming to establish a green AI data center in Johor, Malaysia.
Originally, YTL’s sizable AI data center project was to be shared between Supermicro and Wiwynn. Supermicro’s Johor plant was expected to double capacity with a new line in Q4, but this plan has been delayed due to financial issues. Wiwynn’s nearby plant has also been expanding, enhancing its one-stop manufacturing services and adding advanced cooling technologies such as direct liquid cooling and immersion cooling to handle the redirected order.
Supermicro CEO Charles Liang, speaking at COMPUTEX 2024, previously unveiled the company’s ambitious Malaysia expansion, aiming to double its output to 10,000 server racks per month by Q4. With the expansion now halted, orders have shifted to Wiwynn.
Wiwynn’s new plant in Johor began assembling server racks last October, and a second phase focusing on motherboard production is expected to go online later this year, with potential plans for a third plant.
Economic Daily News reports that Johor, Malaysia’s largest data center investment hub and the ninth-largest in the Asia-Pacific, currently hosts 13 data centers, with four more under construction. The region’s affordable land, water, and power resources, along with its proximity to Singapore, have drawn multinational companies such as Australia’s AirTrunk and Microsoft, which recently acquired land in Johor for a new data center.
(Photo credit: YTL Power)