2020 was undoubtedly a milestone year in the development of TSMC, the leading semiconductor foundry. According to a report from TechNews, TSMC’s global expansion has reached locations in China, the United States, Japan, and Germany, solidifying its goal of being a “long-term and trustworthy provider of technology and capacity.”
On February 24th, TSMC will hold an opening ceremony for the Kumamoto plant, which is scheduled to commence production by the end of the year. With the opening of the Kumamoto plant, let’s review TSMC’s global expansion plan:
Arizona, United States
In May 2020, TSMC officially announced the selection of Arizona, United States, as the location for constructing an advanced process fab.
Initially planned to invest USD 12 billion, the facility aims to build a N5 process fab with a monthly capacity of 20,000 wafers. Construction was scheduled to commence in 2021, with mass production slated to begin by the end of 2024, creating approximately 1,600 job opportunities in the local area. Subsequently, in 2022, TSMC announced plans to start N4 advanced process production at the Arizona fab to meet market demands.
In December 2022, the second phase of construction began at the fab in Arizona, United States. It is expected to commence production using N3 process technology by 2026. The total investment for both phases amounts to approximately USD 40 billion, creating 4,500 jobs opportunities at TSMC.
Upon completion of both phases, the combined annual capacity will exceed 600,000 wafers, with the market value of end products estimated to exceed USD 40 billion. This project ranks as one of the largest foreign direct investment projects in US history.
However, due to the delay in the first phase’s production timeline from the end of 2024 to the first half of 2025, the production schedule for the second phase will also be postponed to start after 2027.
Kumamoto, Japan
In October 2021, TSMC, in collaboration with its customer Sony Group’s wholly-owned subsidiary, Sony Semiconductor Solutions, announced the establishment of a subsidiary called Japan Advanced Semiconductor Manufacturing (JASM) in Kumamoto, Japan. Sony Semiconductor Solutions plans to invest approximately USD 500 million to acquire up to 20% of the shares of JASM.
Following this, Denso, a major Japanese automotive components manufacturer, also announced its investment in JASM. TSMC further increased its investment in the Kumamoto plant, raising the investment amount to nearly JPY 1 trillion.
It plans to introduce 12/16-nanometer processes in addition to the originally planned 22/28-nanometer processes, with a monthly capacity reaching 55,000 wafers. This project has received commitments of support from the Japanese government, with an expected subsidy of approximately JPY 476 billion.
It was previously rumored that one of the shareholders of JASM, Sony Semiconductor, was urged by its customer, Apple, to expedite the production of image sensors (CIS) at the Kumamoto plant. Consequently, trial production began even before the opening of the Kumamoto plant. However, TSMC responded that the production timeline remains according to plan and is scheduled to commence before the end of 2024.
Recently, TSMC announced a new project in collaboration with its Japanese partners Sony Semiconductor, Denso Corporation, and Toyota Motor Corporation to invest in JASM and construct a second fab, scheduled to commence operations by the end of 2027.
TSMC stated that in response to customer demand, construction of the second JASM fab in Japan is slated to begin by the end of 2024. The expansion of production capacity is also expected to optimize the overall cost structure and supply chain efficiency of JASM.
In the future, the two fabs under JASM will enable a total monthly production capacity of over 100,000 12-inch wafers, providing 40-nanometer, 22/28-nanometer, 12/16-nanometer, and 6/7-nanometer processes for automotive, industrial, consumer, and high-performance computing (HPC) applications.
Capacity planning may be adjusted according to customer demand, with the Kumamoto plant directly creating a total of over 3,400 high-tech job opportunities. Through the investment, TSMC, Sony Semiconductor, Denso Corporation, and Toyota Motor Corporation hold approximately 86.5%, 6.0%, 5.5%, and 2.0% of the JASM shares, respectively.
Dresden, Germany
In August 2023, TSMC, along with Robert Bosch GmbH, Infineon Technologies AG, and NXP Semiconductors N.V., jointly announced plans to invest in the European Semiconductor Manufacturing Company (ESMC) located in Dresden, Germany, to provide advanced semiconductor manufacturing services.
TSMC stated that the ESMC represents a significant step forward in the construction of a 12-inch fab to support the future capacity demands in the rapidly growing automotive and industrial markets. The final investment decision is subject to confirmation of government subsidies.
This project is developed within the framework of the European Chips Act. Following approval by regulatory authorities and meeting other conditions, TSMC will hold a 70% stake in the joint venture, while Bosch, Infineon, and NXP will each hold a 10% stake. The fab will be operated by TSMC.
TSMC emphasized that the fab planned for this project is expected to utilize TSMC’s 28/22-nanometer Complementary Metal-Oxide-Semiconductor (CMOS) technology and 16/12-nanometer FinFET processes, with a monthly capacity of approximately 40,000 12-inch wafers.
Through advanced FinFET technology, the aim is to further strengthen the semiconductor manufacturing ecosystem in Europe and create approximately 2,000 direct high-tech job opportunities. ESMC aims to commence construction of the fab in the second half of 2024, with production slated to begin by the end of 2027.
Continuing Advancements in Advanced Processes in Taiwan
In addition to its overseas expansions, TSMC continues to advance its most cutting-edge processes and advanced packaging technologies in Taiwan.
Given the strong demand for N3 process technology over the years, TSMC is expanding the N3 process capacity at its Tainan Science Park. Additionally, in preparation for the commencement of mass production of N2 process technology in 2025, TSMC plans to establish multi-stage N2 process technology capacity in the science parks of Hsinchu and Kaohsiung.
In Hsinchu’s Baoshan area, the first phase has been completed, and TSMC’s Global R&D Center has been in use since 2023. Baoshan Phase Two will serve as the base for TSMC’s N2 process technology.
Additionally, TSMC plans to construct two 2-nanometer advanced process fabs in Kaohsiung. The related land pollution remediation projects are expected to be completed by the end of 2024.
Finally, regarding the urban planning amendment for the expansion of the Central Taiwan Science Park Phase II, which concerns TSMC’s layout for constructing 2-nanometer fabs, TSMC also indicated that the review progress by the Taichung Science Park Administration is proceeding as scheduled.
This development will allow the land in the Central Taiwan Science Park to be handed over to TSMC for use as early as 2024, enabling subsequent commencement of the construction of the fabs.